Il cronoprogramma
del progetto è il seguente:
Task
|
R.U.
|
Duration (months)
|
3
|
6
|
9
|
12
|
15
|
18
|
21
|
24
|
27
|
30
|
33
|
36
|
WP1 - Project Management
|
a
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.1 Financial and technical project
management
|
1
|
6
|
|
|
|
|
|
|
|
|
|
|
|
|
1.2 Preliminary actions
|
1
|
36
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WP2 - Landslide
characterization and physics model definition
|
RU-UNICH/RU-UNIFI
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.1 Physical characterization
of materials
|
4
|
9
|
|
|
|
|
|
|
|
|
|
|
|
|
2.2 Stress characteristics during pre and
incipient failure
|
4
|
21
|
|
|
|
|
|
|
|
|
|
|
|
|
2.3 Recognition and mapping of slope
instability phenomena
|
1,3,6
|
9
|
|
|
|
|
|
|
|
|
|
|
|
|
2.4 Three-dimensional reconstruction of
landslide geometries and soil covers.
|
1,2,3
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WP3 - Analysis
and modelling of triggering conditions
|
RU-UNINA/RU-POLIBA
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.1
Infiltration and water flow modelling
|
1,2,4
|
9
|
|
|
|
|
|
|
|
|
|
|
|
|
3.2 Triggering conditions
analysis
|
5
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
3.3 Triggering conditions analysis by
data-driven models
|
6
|
18
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WP4 - Landslide
spatial prediction
|
RU-UNIBO/RU-UNIMIB
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.1 Landslide
susceptibility by statistical methods
|
2,3
|
6
|
|
|
|
|
|
|
|
|
|
|
|
|
4.2 Source area location by physical models
|
1
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
4.3 Prediction of evolution of slow
landslides
|
4,5,7
|
15
|
|
|
|
|
|
|
|
|
|
|
|
|
4.4 Propagation of granular flows
|
1,2,4,5,7
|
15
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WP5 - Temporal forcast and simulation of rainfall regime changes
|
RU-UNISANNIO/RU-UNIFI
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.1 Rainfall-landslide relationship and
alert thresholds
|
5,6
|
21
|
|
|
|
|
|
|
|
|
|
|
|
|
5.2 Rainfall threshold definition for
landslide triggering on regional and national scales
|
2,3
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
5.3 Hydrological time series analysis and
landslide reactivations
|
1
|
18
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WP6
-Improvement and definition of hazard and risk scenario, Alarm systems
|
RU-UNIMIB/RU-IRPI
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.1 Hazard models
|
7
|
15
|
|
|
|
|
|
|
|
|
|
|
|
|
6.2 Synoptic definition and zonation of risk
|
8
|
18
|
|
|
|
|
|
|
|
|
|
|
|
|
6.3 Quantitative risk assessment
|
2
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6.4 Social Impact prevision
|
2,8
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
6.5 Alert systems
|
5
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
6.6 Improvement of methodologies and
procedures for hazard and risk mapping
|
1,2,3,4,5,6,7,8
|
9
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WP7 - Dissemination
|
RU-UNISANNIO
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7.1 Development of web resources for the
project
|
1
|
36
|
|
|
|
|
|
|
|
|
|
|
|
|
7.2 Dissemination and training
|
1,2,3,4,5,6,7,8
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
|